According
to the investor, Trung Nam Solar Power JSC, a member of Trung Nam
Group, the 204MW plant will cover more than 264 hectares of the Trung
Nam wind farm in Bac Phong and Loi Hai communes, Thuan Bac District.
Work on the plant will start on July 7 and is scheduled to be completed by June 2019.
It is expected to produce between 401 and 450 million kWh of
electricity per year, supplying more electricity for Ninh Thuan Province
in particular and the country in general.
On July 3, the Electric Power Trading Company (EPTC) under
Electricity of Vietnam (EVN) signed a power purchase agreement with the
Trung Nam Solar Power JSC.
Under the agreement, EPTC will purchase electricity from Trung Nam at a price of 2,086 VND (9.35 cents) per kWh.
In August 2016, Trung Nam Group started work on a 100MW wind power plant in the province.
The group has already developed a number of energy projects,
including the 70MW Dong Nai 2 hydropower plant and the Krong No.2 and
Krong No.3 hydropower plants, with a combined output of 48MW, in the
Central Highlands province of Lam Dong. As of November 2017, all of its
hydropower plants had generated more than 1 billion KWh.
Source: VNA